Indiana University - Purdue University Fort Wayne ETCS Roof Replacement

This project included roof replacement (4,329 SF) of all areas in addition to masonry repairs around all elevations. Each roof area was designed with tapered insulation, cover board and a 2-ply modified bituminous roofing membrane system. Fall protection was provided on 1 roof area, otherwise the parapets around perimeters of all other roof areas was either high enough or no equipment was in range of the perimeter. On previous years, we had covered the parapets with pre-finished gi coping to prepare for future roof replacement

PROJECT TEAM

Tony Murray

Jonathan Sitton

Mike Hamilton

Google Map